Ngauranga Station: Shelter Upgrades
Updates
Description
Metlink is looking at all train stations to ensure they provide customers with a safe, comfortable place to wait for their train.
One of the stations getting an upgrade is the Ngauranga Station building which is being upgraded with a new waiting area to keep customers dry and comfortable in harsh weather conditions.
Customer Impact
During the project, customers will need to use the temporary shelter that has been constructed.
Benefits
These upgrades will enhance safety and aesthetics, making the station a more secure and weather resilient space.
Project Timeline
Oct 21 2024
- Dec 20 2024
Phase 1: Demolition of the Current Shelter
Oct 26 - Oct 28
Completed
Phase 2: Installation of New Foundations
Oct 29 - Nov 17
In progress
Phase 3: Installation of the New Shelter
Nov 18 - Dec 12
Not started
Phase 4: Removal of Temporary Shelter
Dec 13 - Dec 20
Not started